Key Theatre, Peterborough
Installing lattice timberwork to support failing RAAC concrete. Carried out an extensive temporary support detail to the roof as designed by the Structural Engineer. Works continued over a period of 6 weeks and finished on time to allow the theatre to reopen for the Christmas Pantomime shows.