Slope Stabilisation at Derrygonnelly Road, Enniskillen
Enniskillen
Slope Stabilisation project.

Stabilisure Ltd · Company NI650263
Active, accounts up to date·engineer & consultant·Head office Belfast
Stabilisure was founded with the goal of developing a quick and cost-effective method for stabilising embankments, reinforcing retaining structures, and improving foundation bearing capacity. The company founders possess decades of experience in the Civil Engineering industry, including expertise in both the design and installation of their proprietary micro soil nail system. This system can be integrated with various facing materials such as precast concrete blocks, steel mesh, geogrids, erosion protection, gabion baskets, and geosynthetic cementitious composite mats to create bespoke solutions.
Stabilisure combines extensive design consultancy with on-site installation experience. Their soil nail system is designed to reinforce existing or proposed retaining systems, slopes, and foundations, offering a solution that can be installed rapidly even in confined working areas. The company aims to minimise costs associated with importing engineered fill, disposing of excavated soil, and additional labour by reinforcing the original soil.
Key personnel include Ross Patterson, Managing Director, with five years of experience in retaining system design and seven years as Managing Director of site investigation company Stratex NI. , and Maccaferri. Gordon also directs the geotechnical consultancy Geoman Ltd.

Enniskillen
Slope Stabilisation project.

Glasgow
MSE Soil Bag Retaining Wall at White Cart River.

Halifax
Segmental Block Retaining Wall.

Stone
Segmental Wall.

Bishopbriggs
Temporary Works.

Shipton-on-Stour
Segmental Wall.

Newtownards
Temporary Works.

Lisburn
Foundation design for the site at Balmoral Park was subject to variable ground conditions and a high water table, therefore Stabilisure soil nails were used to reinforce the soil underneath the RC foundations to provide added confidence in the design. Plate load testing at this site showed that as little as 2 micro soil nails in the subgrade provided a minimum improvement of 12% to the bearing capacity.

Temporary Works at Altnagelvin Hospital.

Cork
Segmental Wall.
This profile was compiled from public records. Claim it to add the things buyers ask for:
Stabilisure offers a unique micro soil nail system for slope stability, retaining structures, and foundation reinforcement. Fast installation in limited spaces. Their listed services include Civil engineering and Groundworks.
Stabilisure Ltd is registered at 44 Elmwood Avenue, Belfast, BT9 6AZ, in Northern Ireland.
Stabilisure Ltd states that it works across Northern Ireland, Scotland, England and Republic Of Ireland.
Accounts filed for the year to 2023 report 4 employees, which places the company in the 10-49 employees band.
Stabilisure Ltd does not disclose turnover: UK small-company accounts are not required to. Based on creditors in its filed accounts, turnover is likely to fall between £320k and £1.3m. This is an estimate, not a filed figure.
Companies House lists Stabilisure Ltd as active, with accounts most recently made up to 2025-01-31.