Underfloor Heating & Liquid Screed Installation Project Overview. The aim of the project was to provide an effective and economical heating system capable of delivering consistent warmth throughout the building while improving comfort for hall users and reducing long-term energy costs. Our team carried out the full installation of the underfloor heating system across the village hall floor area. Careful planning and preparation ensured the pipework was installed accurately and efficiently, providing complete coverage throughout the building. Once the heating system was in place and pressure tested, we completed the project with a high-quality liquid screed installation. The screed was poured to create a smooth, level finish while fully encapsulating the underfloor heating pipes, maximising heat transfer and system performance.